Lobby/Plaza Updates
The following construction updates will inform you what is coming up this week (December 15 - December 22):

Lobby:
• Final hook up of all lights to be completed including aiming and adjustments.
• Continue security desk installation.
• Install garage elevator indicator lights.
• Continue travertine caulking.
• Complete installation of metal panels.
• Complete new stone stairs to retail including the handrail.
• Install stone flooring in mailroom corridor after hours. Access to mailroom will remain open during business hours.
Plaza:
• Complete final geofoam installation.
• Continue installation of pedestal pavers.
• Receive final planter soil delivery for Phase 1 & 2.
• Complete metal panels on portal.
• Complete Phase 3 waterproofing.