Lobby & Plaza Updates
The following construction updates will inform you what is coming up this week (October 13 - October 20):

Lobby:
• Continue travertine installation in elevator lobbies.
• Continue cedar installation around entry.
• Complete entry glass installation.
• Continue elevator renovation.
• Continue work on FirstBank’s new storefront.
• Complete 2nd Floor window relocation.
• Continue installation of light fixtures and pendants in corridor by elevator lobbies.
• Continue installation of floor stone outside of CAZ.
• Complete framing of remaining storefronts.
• Begin installation of new column covers.
• Scaffolding at the Larimer Street ramp remains thru Saturday, October 21st.
Plaza:
• Continue installation of stone on planters.
• Continue laying cobblestone.
• Continue bus pad and sidewalk concrete work.
• Continue geofoam installation.
• Begin plantings.